Overdue & At-Risk Submissions
PM
Project Manager
Overdue
3
Past planned date, not submitted
At Risk (Due in 7 Days)
2
Still in progress
Revise & Resubmit
2
Awaiting correction

⚠ Overdue Submissions — Past Due, Not Submitted

Transmittal Package Building Discipline Planned Date Days Overdue Weightage Impact
TRN-012 Structural Concept Package Building B Structural 20-Mar-2026 18 days 3.0% High — Blocks Preliminary
TRN-013 MEP Concept Package Building B MEP 22-Mar-2026 16 days 3.0% High — Blocks Preliminary
TRN-019 Architectural Preliminary Package Building B Architecture 01-Apr-2026 6 days 6.0% Medium — Delays Detailed

⏱ At-Risk Submissions — Due Within 7 Days

Transmittal Package Building Discipline Planned Date Days Left Current Status
TRN-020 Structural Preliminary Package Building B Structural 10-Apr-2026 3 days In Progress
TRN-021 Architectural Detailed Package Building A Architecture 12-Apr-2026 5 days In Progress

↺ Revise & Resubmit — Awaiting Corrections

Transmittal Package Building Discipline Submitted Reviewed Rev Comments
TRN-015 Architectural Preliminary Package Building A Architecture 28-Mar-2026 03-Apr-2026 Rev A 12 comments — facade cladding details missing, floor plan dimensions inconsistent
TRN-009 Structural Concept Package Building A Structural 22-Feb-2026 01-Mar-2026 Rev 0 5 comments — load assumptions need verification, foundation type TBC