Design Submission Log
PM
Project Manager
Total
37
Approved
8
Under Review
5
In Progress
10
Revise & Resubmit
2
Overdue
3

All Submissions (37 Packages)

S.No Transmittal Phase Building Discipline Package Title Wt.% Planned Submitted Status Rev
MOBILIZATION
1TRN-001MobilizationSite-wideGeneralDesign Management Plan1.015-Jan-202614-Jan-2026ApprovedRev 0
2TRN-002MobilizationSite-wideGeneralCAD/BIM Standards & Protocols0.515-Jan-202615-Jan-2026ApprovedRev 0
3TRN-003MobilizationSite-wideGeneralCommunication & Coordination Plan0.515-Jan-202616-Jan-2026ApprovedRev 0
4TRN-004MobilizationSite-wideGeneralDrawing Numbering Convention0.515-Jan-202614-Jan-2026ApprovedRev 0
5TRN-005MobilizationSite-wideGeneralTeam Organogram & Key Personnel CVs0.520-Jan-202618-Jan-2026ApprovedRev 0
6TRN-006MobilizationSite-wideGeneralQA/QC Plan0.520-Jan-202620-Jan-2026ApprovedRev A
7TRN-007MobilizationSite-wideGeneralHealth & Safety Plan0.520-Jan-202619-Jan-2026ApprovedRev 0
CONCEPT DESIGN
8TRN-008ConceptBuilding AArchitectureArchitectural Concept Package5.015-Feb-202612-Feb-2026ApprovedRev A
9TRN-009ConceptBuilding AStructuralStructural Concept Package3.020-Feb-202622-Feb-2026ApprovedRev 0
10TRN-010ConceptBuilding AMEPMEP Concept Package3.025-Feb-202626-Feb-2026ApprovedRev 0
11TRN-011ConceptBuilding BArchitectureArchitectural Concept Package5.001-Mar-202605-Mar-2026ApprovedRev B
12TRN-012ConceptBuilding BStructuralStructural Concept Package3.020-Mar-2026Overdue
13TRN-013ConceptBuilding BMEPMEP Concept Package3.022-Mar-2026Overdue
14TRN-014ConceptCommon AreasLandscapeLandscape Concept Package2.010-Mar-202608-Mar-2026ApprovedRev 0
PRELIMINARY DESIGN
15TRN-015PreliminaryBuilding AArchitectureArchitectural Preliminary Package6.015-Mar-202628-Mar-2026Revise & ResubmitRev A
16TRN-016PreliminaryBuilding AStructuralStructural Preliminary Package4.020-Mar-202625-Mar-2026Under ReviewRev 0
17TRN-017PreliminaryBuilding AMEPMEP Preliminary Package4.025-Mar-202630-Mar-2026Under ReviewRev 0
18TRN-018PreliminaryBuilding AInterior DesignInterior Design Preliminary Package3.001-Apr-202602-Apr-2026Under ReviewRev 0
19TRN-019PreliminaryBuilding BArchitectureArchitectural Preliminary Package6.001-Apr-2026Overdue
20TRN-020PreliminaryBuilding BStructuralStructural Preliminary Package4.010-Apr-2026In Progress