Design Management — Pau Development
7 Buildings • 6 Disciplines • 37 Submission Packages • 24-Month Programme
Total Packages
37
100% Weightage
Approved
8
21.6% Complete
Under Review
5
13.5% of Total
In Progress
10
27.0% of Total
Overdue
3
Requires Attention
Revise & Resubmit
2
5.4% of Total
Overall Project Progress (by Weightage Earned)
21.6% Complete
■ Approved: 21.6%
■ Under Review: 13.5%
■ In Progress: 27.0%
■ Not Started: 37.9%
Progress by Design Phase
| Mobilization | 7/7 | |
| Concept Design | 1/7 | |
| Preliminary Design | 2/6 Submitted | |
| Detailed Design | 1/5 In Progress | |
| Construction Docs | 0/4 | |
| Construction Support | 0/3 | |
| Closure | 0/5 |
Building Status at a Glance
| Building | Concept | Preliminary | Detailed | IFC |
|---|---|---|---|---|
| Building A | Approved | Under Review | In Progress | Not Started |
| Building B | Approved | In Progress | Not Started | Not Started |
| Building C | Under Review | Not Started | Not Started | Not Started |
| Building D | In Progress | Not Started | Not Started | Not Started |
| Building E | In Progress | Not Started | Not Started | Not Started |
| Common Areas | Approved | Not Started | Not Started | Not Started |
Recent Submissions
View All →| Transmittal | Package | Building | Discipline | Submitted | Status | Rev |
|---|---|---|---|---|---|---|
| TRN-018 | Interior Design Preliminary Package | Building A | Interior Design | 02-Apr-2026 | Under Review | Rev 0 |
| TRN-015 | Architectural Preliminary Package | Building A | Architecture | 28-Mar-2026 | Revise & Resubmit | Rev A |
| TRN-016 | Structural Preliminary Package | Building A | Structural | 25-Mar-2026 | Under Review | Rev 0 |
| TRN-011 | Architectural Concept Package | Building B | Architecture | 15-Mar-2026 | Approved | Rev B |
| TRN-008 | Architectural Concept Package | Building A | Architecture | 10-Mar-2026 | Approved | Rev A |
⚠ Overdue Submissions
View Details →| Transmittal | Package | Building | Planned Date | Days Overdue | Status |
|---|---|---|---|---|---|
| TRN-012 | Structural Concept Package | Building B | 20-Mar-2026 | 18 days | Overdue |
| TRN-013 | MEP Concept Package | Building B | 22-Mar-2026 | 16 days | Overdue |
| TRN-019 | Architectural Preliminary Package | Building B | 01-Apr-2026 | 6 days | Overdue |