Project Overview Dashboard
PM
Project Manager

Design Management — Pau Development

7 Buildings • 6 Disciplines • 37 Submission Packages • 24-Month Programme

📋
Total Packages
37
100% Weightage
Approved
8
21.6% Complete
🔍
Under Review
5
13.5% of Total
In Progress
10
27.0% of Total
Overdue
3
Requires Attention
Revise & Resubmit
2
5.4% of Total

Overall Project Progress (by Weightage Earned)

21.6% Complete
21.6%
Approved: 21.6% Under Review: 13.5% In Progress: 27.0% Not Started: 37.9%

Progress by Design Phase

Mobilization
7/7
Concept Design
1/7
Preliminary Design
2/6 Submitted
Detailed Design
1/5 In Progress
Construction Docs
0/4
Construction Support
0/3
Closure
0/5

Building Status at a Glance

Building Concept Preliminary Detailed IFC
Building A Approved Under Review In Progress Not Started
Building B Approved In Progress Not Started Not Started
Building C Under Review Not Started Not Started Not Started
Building D In Progress Not Started Not Started Not Started
Building E In Progress Not Started Not Started Not Started
Common Areas Approved Not Started Not Started Not Started

Recent Submissions

View All →
Transmittal Package Building Discipline Submitted Status Rev
TRN-018 Interior Design Preliminary Package Building A Interior Design 02-Apr-2026 Under Review Rev 0
TRN-015 Architectural Preliminary Package Building A Architecture 28-Mar-2026 Revise & Resubmit Rev A
TRN-016 Structural Preliminary Package Building A Structural 25-Mar-2026 Under Review Rev 0
TRN-011 Architectural Concept Package Building B Architecture 15-Mar-2026 Approved Rev B
TRN-008 Architectural Concept Package Building A Architecture 10-Mar-2026 Approved Rev A

⚠ Overdue Submissions

View Details →
Transmittal Package Building Planned Date Days Overdue Status
TRN-012 Structural Concept Package Building B 20-Mar-2026 18 days Overdue
TRN-013 MEP Concept Package Building B 22-Mar-2026 16 days Overdue
TRN-019 Architectural Preliminary Package Building B 01-Apr-2026 6 days Overdue